FABIERBuilding Performance
← All projects

Owlstone Croft, Cambridge

Design, supply, installation, testing and certification of six separate Class IV lightning protection systems to two accommodation blocks and four terraces, plus a UKPN substation earth.

Client
Munro Building Services, for Morgan Sindall Construction
Location
Owlstone Road, Newnham, Cambridge
Sector
Student accommodation
Year
2025 to 2026

6

Structures protected

£18,900

Contract value

IV

Protection class

Owlstone Croft is a student housing development of six structures: Blocks A and B and Terraces 1 to 4. Each building needed its own protection zone under BS EN IEC 62305 rather than one shared system. The metallic mansard roofs had been proposed as the perimeter air termination, which is only acceptable if the mansard is proven electrically continuous. The programme was phased over 2025 and 2026, so our attendances had to follow each block in turn, and the site also needed a UKPN standard substation earth before the switchgear could go in.

  • Designed six individual Class IV systems to BS EN IEC 62305 and the project specification. Each block and terrace got its own air termination network, down conductors and earth termination system, so no building relies on another for its path to ground.
  • Continuity tested the metallic mansards before accepting them as the perimeter conductor. Where the mansard proved sound it was used as a natural air termination; the roof plant, heat pumps, MVHR units, ductwork and structural metalwork on Block B were bonded in, with tape carried across the plant room roof.
  • Bonded the structure at each down conductor position and installed each building's earth termination system with test clamps.
  • Under a separate instruction, designed and installed the earthing for the site's UKPN substation to the UKPS earthing drawing: 40 x 6 mm aluminium marshalling bar 300 mm above finished floor level, copper bonded rods driven in 1.2 m sections to 4.8 m, 70 mm squared green and yellow rod and mesh connections, and BS 7430 testing with a standalone certificate to UKPS before the equipment went in.
  • Issued test and commissioning certification, as fitted drawings and O&M manuals for each structure. Surge protection was excluded and written to the electrical contractor under BS EN 62305-4.

Six independent systems delivered under a JCT sub contract order valued at £18,900 excluding VAT (Blocks A and B £9,700, Terraces 1 to 4 £9,200), with a 12 month defects period. The client has given a written project reference.

  • BS EN IEC 62305:2024 Parts 1 to 4
  • BS EN 62561
  • BS 7430:2011
  • UKPN substation earthing standard EDS 07-3102